Maintenance Timing
Medium
Jan 29Defer C-Check on A7-AAA to align with lease return
A7-AAA has a C-Check scheduled for Q3 2026, but the lease expires in Q4 2026. Deferring the C-Check and performing it as part of redelivery could eliminate duplicate inspection costs.
Potential Cost Savings
$661,783
Source
Maintenance Schedule Analysis
Current State· Before recommendation
Scheduled C-Check (Q3)Standalone C-Check event
Redelivery C-Check (Q4)Required check at redelivery
Aircraft downtime costsRevenue loss during checks
Total Projected Cost$1.89M
Recommended State· After recommendation
Combined redelivery C-CheckSingle consolidated check
Single downtime periodReduced revenue impact
Total Projected Cost$1.23M
Before
$1.89M
After
$1.23M
You Save
$662K
AI Reasoning
The lease return conditions require a fresh C-Check at redelivery. Performing a C-Check now and again at redelivery would result in approximately $1.8M in avoidable maintenance costs. The aircraft is currently within deferral limits per the MPD.
Recommended Action
Obtain deferral approval from QCAA and lessor technical team. Update maintenance planning schedule.
Affected Aircraft & Leases
Generated Jan 29 via Maintenance Schedule Analysis